Request For Quote, Installation of Solana Trees

Installation of 3 x Deger D-60 Trackers
The subcontractor will perform these essential services on site.
  1. Dig foundations.
  2. Trench.
  3. Pour or place pre-cast concrete x 3 per the Structural Engineering schematics.
  4. Install Deger D-60 mast, motor and electrical service, accessories including wind sensor and Maximum Light Detection sensors, PV Inverters on mast and make the structure operational in all respects except the delivery of electricity from structure.
  5. Mount PV Modules (24 per mast) on Surface Area per the guidance of the Contractor.
  6. Operate electrically the movement of the mast and the array. 
  • Structural Engineering
  • Current Design Schematic.
  • Current Project Requirements.
  • Deger D-60 Spec.
  • Soils Report.
  • Wind Report.
  • Site Layout
  • D-60 Layout Tool, 30d Latitude.
Powered by Create your own unique website with customizable templates.
  • Home
  • About
    • Case Study
    • For Building Owner/Users
    • REITS Owner/Users & Realtors
    • Transform Energy Asset
    • Mission & Careers
  • Contact